Click to Home
Irvington Connect

Go To Search
Project Status
The following major projects are currently underway.  This page will be updated to reflect current information about schedules, road closures, or any other important information.


Station Road Culvert Replacement Project
The Village is undertaking the replacement of a culvert that carries Barney Brook beneath Station Road near the intersection of Brook Place. A contract has been awarded to McNamee Construction to complete this work.

Major construction is not expected to take place until mid-July.  Work is expected to last through the summer.  At some point during construction, Station Road will be closed to all through traffic.

A more detailed schedule will be posted when available.


Paving 2017
The Village DPW will be paving the full length of upper Fieldpoint Drive during the late summer / early fall of 2017.  Bids are due back June 28, 2017.  When a contract is awarded, a more detailed schedule will be posted.


Old Croton Aqueduct Trailway Improvement Project
Helped by a $230,500 NYS Parks grant, the Village will be undertaking certain improvements at the intersection of the Old Croton Aqueduct Trailway and Main Street.  The improvements include the enhancement of the crosswalks, rehabilitated war memorials, and the construction of a trail connecting Main Street to the OCA trail headed to the north (adjacent to the Main Street School parking lot).

A contract was awarded to Tony Casale, Inc.  Work is expected to begin during the second week of July and continue through the summer of 2017.

The following is the upcoming schedule:

Monday 7/10
Mobilize/Layout/Cones, Barrels and Orange Fence around work area (half of school parking lot, and parking east of trees or high ground) for tree clearing

Tuesday 7/11
Shrub Removals

Wednesday 7/12-Friday 7/14
Major Tree Clearing
Removals around Monument Area

Monday 7/17- Friday 7/21
Stumping/Excavation/Wall
Electrical Conduit & Panel Rotation

Please note, there will no parking allowed on Aqueduct Lane 7/12-14.  And then for 2-3 weeks beginning on 7/17. Residents of Aqueduct Lane may park in the Aqueduct Parking Lot without a permit.